TM 5-3895-367-14&P
(6)
Install two eyebolts (3), new lockwashers (2),
and nuts (1) to secure operators platform (4) to
hopper.
(7)
Using gate adjusting lever (6), open and close
hopper gate. If there is any interference
between operators platform (4) and gate, adjust
clearance as follows:
(a)
Loosen setscrew (7) in each housing (8).
(b)
Slide telescopic pipes (9) in or out of
housings (8) until gate opens and closes
freely. Tighten setscrews (7).
(8)
Tighten operators platform mounting eyebolts
(3) to 216 lb-ft. Ensure that openings in eyebolts
face sides of spreader.
4-25