TM 5-3895-367-14&P
4-22. OPERATORS PLATFORM REPAIR (CONT).
NOTE
Steps (2) through (4) are for the left-hand frame
support and rail.
All of the quick-release pins are installed the
same way. Step (2) is for one quick-release pin.
Repeat as necessary for the other quick-release
pins.
(2)
Install quick-release pin (16) using screw
(21).
(3)
Slide support bracket (19) over rail (17).
Secure support bracket to rail using quick-
re- lease pin (20)
(4)
Push rail (17) into frame support (18) and
secure in lowest position using two quick-
re- lease pins (16).
NOTE
Steps (5) through (9) are for right-hand
frame sup- port and rail.
(5)
Install spring (15), flatwasher (14), and
handle (13) on gate (5) and secure with
new cotterpin (12).
NOTE
All of the quick-release pins are installed the same way.
Step (6) is for one quick-release pin. Repeat as
necessary for the other quick-release pins.
(6)
Install quick-release pin (1) on frame
support (3) using screw (11).
(7)
Install gate (5) on frame support (3) using
two screws (10), new lockwashers (9), and
nuts (8). Tighten gate mounting screws to
25 lb-ft.
(8)
Slide support bracket (6) onto rail (2).
Secure support bracket to rail using quick-
release pin (7).
(9)
Slide rail (2) through gate (5) and into
frame support (3).
FOLLOW-ON MAINTENANCE:
If spreader is being prepared for use, install
operators platform on spreader (para 4-14). If
spreader is being prepared for transport or
storage, stow operators platform in hopper (para
4-12).
4-40